Do I need EN 1090 certification?

EN 1090 is the harmonised standard that outlines how to lawfully place fabricated structural metalwork on the European market under the Construction Products Regulation (CPR).

There are two additional sections working together with the harmonised standard EN 1090-1 covering conformity assessment itself.

They work together, but each has a different job:  

  • Part 2 covers how steelwork must be manufactured and assembled 
  • Part 3 covers how aluminium must be manufactured and assembled 

EN 1090 is legally required for manufacturers, fabricators, assemblers, and suppliers who produce or place load-bearing structural steel or aluminium components onto the market in the UK or the European Union/EEA. 

overlay weld

How do I comply with EN 1090? 

EN 1090 requires the following steps: 

  • Factory Production Control (FPC): This is required under EN 1090-1. that means, you must establish and maintain an internal FPC system to monitor manufacturing consistency.  
  • Welding Quality Management: Required under EN1090-2 and –3, it covers performance of welding operations in strict conformity with ISO 3834, complete with qualified welding procedures and a certified Responsible Welding Coordinator (RWC).  
  • Initial Type Testing / Calculation (ITT / ITC): Determine product characteristics through initial type tests or structural calculations.  
  • Third-party certification: Undergo an initial audit and continuous surveillance audits by an independent Notified Body, like HPiVS.  
  • Declaration of Performance (DoP) and CE Marking: Finally, issue a DoP detailing the structural performance and affix the CE mark to the components before selling or delivering them to a site. 

EN 1090-1 Factory Production Control requirements 

Factory Production Control (FPC) under EN 1090-1 is a documented, continuous quality management system. It commonly covers areas including: 

  • Materials – covering traceability and verification of raw steel or aluminium sheets, sections, and fasteners 
  • Manufacturing processes – controlling cutting, forming, assembly, and surface treatments (such as galvanizing or painting) 
  • Welding procedures – including appointment of competent welders 
  • Testing and calibration – covering maintenance of inspection, measuring, and test equipment 

 

How do I get my FPC system audited? 

An independent Notified Body, like HPiVS, audits and certifies your FPC system. 

 

What is a Factory Production Control Execution Class? 

Your Factory Production Control certificate will outline the maximum Execution Class that a manufacturer is qualified to produce. 

  • EXC1: Low-risk structures (for example, agricultural buildings). 
  • EXC2: Standard residential and commercial buildings. 
  • EXC3 and EXC4: High-risk or complex structures (for example, bridges, large span stadiums and crane tracks). 
Pressure Equipment Directive compliance and certification

How does EN 1090-1 work with Harmonised Standards EN 10025, EN 10210, EN 10219, EN 10088, and EN 15088 – structural metallic products? 

Harmonised Standards EN 10025, EN 10210, EN 10219, EN 10088, and EN 15088 – structural metallic products cover the raw materials being used. 

For example, a manufacturer purchases raw steel, which has been certified under EN 10025. Then welding, cutting, and drilling etc will be covered according to the quality requirements to create the finished structural steel product. This manufactured product will then get a CE mark under EN 1090-1, which is backed by the material traceability of EN 10025. 